Elphinstone stampede: Piyush Goyal forms panel to probe delay in issuing tender for foot overbridge

Piyush Goyal formed a high-powered committee to look into 18-month delay in issuing a tender for a foot-over-bridge at Elphinstone Road station

Advertisement
|Oct 11, 2017, 22:33:02 IST
New Delhi: Railway Minister Piyush Goyal formed a high-powered committee on Wednesday to look into the 18-month delay in issuing a tender for a foot-over-bridge (FOB) at the Elphinstone Road station in Mumbai, where 23 people were killed in a stampede last month.The two-member committee would inquire why it had taken 18 months after the project was cleared to issue the tender, railway spokesperson Anil Saxena told PTI.The tender was incidentally floated on 29 September, the day 23 people were killed in the stampede on the existing decades-old foot-over bridge.[caption id="attachment_4131773" align="alignleft" width="380"]File image of Elphinstone Road station where a stampede took place on 29 September. PTI

File image of Elphinstone Road station where a stampede took place on 29 September. PTI[/caption]The panel will be headed by former Central Vigilance Commissioner (CVC) Pratyush Sinha and Vinayak Chatterjee of the Confederation of Indian Industries (CII) will be its member."The committee has been given three months to submit its report," Saxena said.According to officials, the committee has also been asked to recommend ways to ensure that such delays do not occur again.The 40-foot-wide overbridge was announced in the 2016 Railway Budget and was part of the Rs 45 crore fund earmarked towards escalators, foot-over bridges and automatic ticket vending machines for the Mumbai suburban section.On Wednesday, an inquiry into the stampede blamed the heavy rain for the tragedy, the officials said.Goyal, while speaking at an event in Delhi, said that he was pained that despite the new foot overbridge being already approved, the tender was not floated in time."It pained me in Mumbai when I saw the file where a foot overbridge which was approved but it took months to finalise the design and prepare the documentation to tender it. wake-up call for all my colleagues in the railways. They will have to bring speed and efficiency into our system," he said.

Handpicked stories, in your inbox
Global stories. Indian perspective. Zero noise.
No Spam. Unsubscribe Any Time.
First Published:Oct 11, 2017, 18:24:13 IST
Advertisement
Advertisement
Trending Stories

'From make in India to launch from India': Skyroot COO on why Vikram-1 could change India’s space sector

Skyroot Aerospace’s successful Vikram-1 mission marks a major milestone for India’s private space sector, as the country seeks to shift from “Make in India” to “Launch from India” and compete in the global commercial satellite launch market
8 min read
Advertisement
Advertisement
Up Next