RINL suffers steep production loss due to heavy rains in Andhra

Raw material supplies, including iron ore coal and coking coal, from Gangavaram and Visakhapatnam Ports were stopped as the operations at the ports were affected due to heavy rains.

Advertisement
FP Archives|Dec 20, 2014, 23:40:39 IST

Hyderabad: The incessant rains lashing Andhra Pradesh for the past five days have impacted the production of Rashtriya Ispat Nigam Limited (RINL), the corporate entity of Vizag Steel, by 60-70% as raw material supplies were hit, according to official sources.

The steel maker normally produces 12,000 to 13,000 tonnes of steel every day.

Advertisement

Raw material supplies, including iron ore coal and coking coal, from Gangavaram and Visakhapatnam Ports were stopped as the operations at the ports were affected due to heavy rains.

[caption id="attachment_1077981" align="alignright" width="380"]Reuters Reuters[/caption]

The sources said as most of the coal is kept at the port itself, the RINL plant is not able to draw coal as the conveyor belt could not transport coal in dampened condition.

businessMore from Business

Coal is used for RINL's captive power plant while coking coal is used in steel making.

"We get coal from Talcher coal mines and coking coal from Australia. As operations from both the ports were hit by the rains supplies have been affected forcing us to cut down the production. The current production levels for the past 4 to 5 days stand at 30% to 40%," sources told PTI.

Advertisement

The PSU imports more than 3.5 million tonnes of cooking coal per annum from Australia to meet its requirements. Talcher Coalfield is located in Angul district in the Indian state of Odisha.

According to sources, the steel maker has three furnaces. Out of these, one is under capital repair and another one is a new one which is yet to meet 100% capacity utilisation.

"We are doing our best to maintain the production. The production may be affected for another 5 to 6 days. Most of the coal became slurry due to continuous rains," sources said.

The conveyor belt which transports coal from Gangavaram Port to the steel plant was not functioning due to non-supply of stocks and may require thorough check after the situation comes to normalcy, they added.

RINL is currently working on expansion, after which the steel-making capacity will increase to 6.3 million tonnes per annum (MTPA), from the existing 3 MTPA.

Gangavaram Port in a statement said that the operations at their port have been going on regularly but the continuous rains have affected the overall efficiency by reducing the discharge rates and dispatches. Also, fertiliser vessel operations have been stopped completely.

Advertisement

PTI

Handpicked stories, in your inbox
Global stories. Indian perspective. Zero noise.
No Spam. Unsubscribe Any Time.
First Published:Oct 28, 2013, 08:13:49 IST
Advertisement
Advertisement
Trending Stories

No premium queues, 30-minute target: What changes for Indian passport applicants in UAE

Indian passport applicants in the UAE can now access passport, visa and attestation services through Alhind’s 16 centres, with no premium queues, a Dh19 service fee and a target of completing applications within 30 minutes
4 min read
Advertisement
Advertisement
Up Next