Advertisement
Co Presented By
Co Presented By

Cabinet approves Power System Development Fund

The fund will also be utilised towards installation of shunt capacitors, series compensators and other reactive energy generators for improvement of voltage profile in the grid. <br /><br />

Advertisement
FP Archives|Dec 21, 2014, 02:41:01 IST

New Delhi: The government today approved the proposal of the Ministry of Power for operationalisation of the Power System Development Fund.

"Power System Development Fund (PSDF) will be utilised for creating necessary transmission systems of strategic importance based on operational feedback by Load Dispatch Centers for relieving congestion in Inter-State Transmission Systems," Finance Minister P Chidambaram told reporters here after the cabinet meeting. Power funds. Reuters

Power funds. Reuters

The fund will also be utilised towards installation of shunt capacitors, series compensators and other reactive energy generators for improvement of voltage profile in the grid.

It will be also used for installation of standard and special protection schemes, pilot and demonstrative projects, and for setting right discrepancies identified in protection audits on regional basis.

Advertisement

Renovation and Modernisation (R&M) of transmission and distribution systems for relieving congestion and any other scheme or project in furtherance of the above objectives, such as, conducting technical studies and capacity building, etc.

PSDF will be operationalised within three months, he said.

PTI

Handpicked stories, in your inbox
Global stories. Indian perspective. Zero noise.
No Spam. Unsubscribe Any Time.
First Published:Jan 02, 2014, 22:13:35 IST