Delay in power plant? Blame BHEL

NLC's latest project to add 1,500 mega watt of power to the grid in Tamil Nadu which is suffering from power shortage, could not be completed as Bhel did not deliver equipments on time.

Advertisement
FP Staff|Dec 20, 2014, 08:51:38 IST

Power companies Neyveli Lignite Corporation and National Thermal Power Corporation have blamed Bhel for delay in power projects in at least two separate cases, according to Business Standard.

Business Standard reports NLC's latest project to add 1,500 mega watt of power to the grid in Tamil Nadu which is suffering from power shortage, could not be completed as Bhel did not deliver equipments on time.

Advertisement

Even NTPC along with other state governments like that of Rajasthan has complained about the same things, Business Standard says. A recent report quoted the Central Electricity Authority as saying, "BHEL has failed to meet the deadline in nine of the 17 thermal projects that were to be commissioned last financial year."

businessMore from Business

[caption id="attachment_328009" align="alignleft" width="380" caption="Agencies"][/caption]

There are many such projects that have allegedly faced delays due to Bhel, including a 2x800-Mw super critical project at Udangudi, 1,000-Mw thermal power project at Tuticorin, and a Rs 5,000 crore project at Vallur.

According to the 11th Plan working group report, 14 percent of the planned capacity was missed because of BHEL's failure to provide equipments.

Advertisement

But Bhel does not accept these charges. Business Standard quotes a senior official from Bhel who says, "People are giving you a wrong impression. BHEL's scope in any of these power projects is only 45-50 percent. We cannot be blamed . We are responsible for boiler turbines while the balance of plant (BoP) is handled by others."

However, if execution of orders remain an issue with Bhel, it will of course create better opportunities for Chinese players and other Indian players like L&T.

Handpicked stories, in your inbox
Global stories. Indian perspective. Zero noise.
No Spam. Unsubscribe Any Time.
First Published:May 31, 2012, 18:00:47 IST
Advertisement
Advertisement
Trending Stories

No premium queues, 30-minute target: What changes for Indian passport applicants in UAE

Indian passport applicants in the UAE can now access passport, visa and attestation services through Alhind’s 16 centres, with no premium queues, a Dh19 service fee and a target of completing applications within 30 minutes
4 min read
Advertisement
Advertisement
Up Next