NASA's Boeing rocket over budget, may delay test launch for deep-space missions
Delivery of the SLS rocket's core stage has already fallen 2.5 years behind, to December 2019: Audit


Artistic representation of NASA Space Launch System spacecraft. Image courtesy: NASA[/caption]“The agency continues to plan for the launch of Exploration Mission-1 in 2020, but there are still technical and schedule risks,” she said in an email.Boeing spokeswoman Patricia Soloveichik said in an email that the audit did not accurately describe the current state of the program and the company had already implemented some of the watchdog’s recommendations. She also blamed “internal NASA issues.”Boeing, which was selected as the main contractor for the NASA program in 2012, has faced delays with other federal contracts.The company has missed several deadlines for delivering its KC-46 aerial refueling tanker to the US Air Force. It has amassed roughly $ 3 billion in costs on the program, a derivative of its 767 commercial aircraft, and is more than two years behind schedule.In the case of the NASA program, Boeing will exhaust the contract’s entire $ 6.2 billion budget three years before it is scheduled to end and ultimately spend $8.9 billion through 2021 without delivering the rocket’s core stage or its upper stage, the report said. The audit blamed insufficient staffing and improper assembly of factory tools for the delays.The larger figure is double the contract’s initial budget.

Careless Whispers: Scientists discover that plants can 'talk' to each other using smells
Life on Mars? European Space Agency’s Orbiter discovers ice water deposits at equator
Microsoft briefly overtakes Apple as the most valuable company, Apple back on top again
Even NASA is facing a tough time, starts layoffs following major budget cuts
ISRO, NASA's NISAR satellite to get ready by Jan-end, will monitor Earth's snow-covered regions