94 infrastructure projects facing delay, cost overrun, says government

Law and order, delay in land acquisition, geological conditions, delay in environment and forest clearances, rehabilitation and resettlement, local body permissions, utility shifting, contractual issues are among major reasons behind the delay and cost override, minister D V Sadananda Gowda said.

Advertisement
|Mar 22, 2017, 18:56:55 IST

New Delhi: Big infrastructure projects worth Rs 150 crore and above are running behind schedule and have cost overrun, Parliament was informed today.[caption id="attachment_2737540" align="alignleft" width="380"]Reuters Reuters[/caption]As many as 1,186 such projects were under the monitoring of the ministry at the end of December 2016, Minister of Statistics and Programme Implementation D V Sadananda Gowda said in a written reply in Lok Sabha."Of these 1,186 projects, 94 projects are delayed and showing cost overruns. The reasons for delay are project specific," Gowda said.Ministry of Statistics and Programme Implementation monitors ongoing central sector infrastructure projects costing Rs 150 and above on time and cost overruns.Law and order, delay in land acquisition, geological conditions, delay in environment and forest clearances, rehabilitation and resettlement, local body permissions,utility shifting, contractual issues are among major reasons behind the delay and cost override, he said.At times these factors also result in non-utilisation of funds fully, the minister said this in a response to a query on number of such projects, cost and time overruns and measures taken to avoid them.Steps like rigorous project appraisal, setting up of standing committees, computerised monitoring system, fixation of duties, project coordination between states and centre to remove bottlenecks are being taken to make projects speedy, he said.

Handpicked stories, in your inbox
Global stories. Indian perspective. Zero noise.
No Spam. Unsubscribe Any Time.
First Published:Mar 22, 2017, 18:40:13 IST
Advertisement
Advertisement
Trending Stories

Tesla sells more cars but makes less money: Why Musk’s AI pivot is squeezing profits

Tesla’s record Q2 deliveries failed to translate into higher profits as price cuts, falling regulatory-credit revenue and Elon Musk’s aggressive AI spending squeezed margins and pushed the EV maker into negative free cash flow
5 min read
Advertisement
Advertisement
Up Next